MB Bldg. Elevator Project

July 10, 2014
|
By Claudie Boujaklian


The project to replace the machinery in all 6 elevators in the MB building will start on July 28 with elevator #3.   The cabin will remain the same as only the machinery and equipment will be replaced.  To minimize the inconvenience only one elevator at a time will be out of service and each elevator will require 5 weeks of work.   We anticipate that this project should be completed by Summer 2015.

We regret any inconvenience this may cause you and we thank you for your patience and understanding.




Back to top