Skip to main content
notice

CC Building: Roof replacement project - June 11 - August 31, 2024 (07:00 to 16:00)

June 10, 2024
|
By Khoba Sysavane


To the users and occupants of the CC Building,

As part of the Project CC Roof Replacement, work will be conducted on the exterior of the Central CC building. The project is scheduled to begin on Tuesday, 2024-06-11, between the hours of 07:00 and 16:00.  We anticipate the completion of this project by the end of August 2024. Please note that this timeline may be adjusted due to weather conditions. A separate notice for the interior work will be provided at a later date. 

 Building

      ·       L- CC / Central Building

 General Information

●        Repair work will be done on all the roofs of the building.

●        Construction noise is expected, but we will make every effort to minimize disturbances.

●        The perimeter of the construction site will be delimited by construction fences.

●       Building access will remain normal, except for access to the west of the building, which will not be authorized during the work.

●      Access inside the building will be normal, with limited access to the 4th floor.

Any change to the current plan will be communicated in a timely manner.

We thank you for your understanding.

Project Management
Facilities Management




Back to top

© Concordia University