Hall Building: Renovation of the linear drain and surrounding concrete - August 5 - 9, 2024 (04:30 - 17:00)

August 2, 2024
|
By Vanessa Petrillo


To the users and occupants of the Hall Building,

A planned renovation of the Hall Building linear drain and surrounding concrete is SCHEDULED to take place from Monday, 2024-08-05 to Friday, 2024-08-09 between the hours of 04:30 and 17:00.  

Building

  • S- Hall / Henry F. Hall Building


General Information

  • The concrete topper, waterproofing membrane, and drain will be demolished and reconstructed.
  • The work zone and ramp will be sectioned-off and remain inaccessible to building occupants throughout the duration of the work.
  • Building users will be given access to all other areas beyond the work zone.
  • There will be noisy work on Wednesday, August 7th between 04:30 and 09:30 that may affect the activities of building occupants.
  • Signage and hearing protection will be posted at loading dock entry points on August 7th .
  • People accessing the loading dock area are required to wear hearing protection during noisy work.
  • Heavy vehicles will not be permitted to drive over the linear drain between August 5th and September 8th during concrete curing period.
  • A temporary protective board will be installed over the linear drain between August 5th and September 8th to allow for the light traffic crossing (up to 600lbs).
  • Full access to the ramp on H-030-1 will be restored on September 9th.


We thank you for your understanding.