UPDATE: Hall Building: Planned construction work on the terrace and H7, H6, and H5 - August 12 - 17, 2024
To the users and occupants of the Hall Building,
Planned work in the alley on the terrace and work on H7, H6, and H5 of the Hall Building is SCHEDULED to start this week.
- Work in the alley planned from Monday, 2024-08-12 at 7:00 to Friday, 2024-08-16 at 15:00.
- Work on H7, H6, H5 planned as night time work from Monday, 2024-08-12 at 23:00 to Saturday, 2024-08-17 at 07:00.
This work is required as part of the Hall Stair Renovation project (21-017).
Building
- S- Hall / Henry F. Hall Building
General Information
Work in the alley:
- Welding of the pilon extensions for the retaining wall will continue.
- The roof will be cut from the existent reservoir room.
- Removal of the existent diesel reservoirs will take place.
- This work will be noisy.
Work on H7, H6, and H5:
- The work will be done overnight throughout the week between the hours of 23:00 and 07:00.
- Cutting of the openings in the floors for the stairwell installation preparation will begin.
- Work will begin on H7 then move to H6 and then H5.
- This work will be noisy.
We thank you for your understanding.
Project Management