RA, PC, and PB Buildings: Interruption of regular electrical power - September 30, 2024 (04:00 - 05:30)
To the users and occupants of the RA, PC and PB Buildings,
A planned interruption of regular electrical power is SCHEDULED for Monday, 2024-09-30, between the hours of 04:00 and 05:30. This interruption is required to allow for a panel shutdown and subsequent connection of a new panel located in the RA building. The work being carried out is in relation to the renovation project #18-098 RA Renovate Gym.
Buildings
• L- RA / Rec & Athletics Building
• L- PC / Perform Center
• L- PB Building
General Information
• This interruption will take place outside of the buildings’ operating hours, therefore no impacts on activities are foreseen.
• No overnight activities are planned in the PC complex during this period.
• A Concordia electrician will be present throughout the shutdown to ensure all systems are in order.
We thank you for your understanding.
Project Management
Facilities Management